CONSTRUCTION TIMELINE

The 1060 project aims to preserve Wrigley Field's beauty, charm and historic features that fans have cherished for more than a century, while updating and improving the iconic ballpark for fans, players and the community.

2016-17 OFFSEASON PROJECTS

To continue playing Cubs baseball at the corner of Clark and Addison streets, the majority of construction work will occur during the offseason. Here's a list of projects that will be executed during this offseason:

  • Home and Visiting Team's Bullpen Relocation
  • New Seating Area in the Bullpens' Former Location
  • Visiting Team Batting Tunnel
  • Partial Fa├žade Restoration on Addison Street
  • Structural Improvements in Right Field
  • Continued Terrace Reserved Seating Replacement
  • Replacement of Seats Behind Home Plate

The following projects will begin during the offseason with work continuing during the 2017 season:

  • American Airlines 1914 Club (to be completed by Opening Day 2018)
  • Concession improvements near Gate F (to be completed during 2017 baseball season)

The following Hickory Street Capital projects will take place during the offseason with work continuing during the 2017 season:

  • Office Building and Plaza
  • Hotel